Claims  |
|
|
What is claimed is:
1. A method to aid in the design of an operation having timing
interactions, by operating a computer system including a processor, a
memory, a means for entering data and a display, the method comprising the
steps of:
(a) generating with said processor a dependence list data structure from a
set D of dependence information entered into the memory, the dependence
information describing timing relationships between first and second
events of each dependence of the operation and describing each dependence
as a primary dependence or secondary dependence;
(b) generating an event list data structure in the memory from the
dependence list data structure, said events identified in one or more of
said primary class dependences being primary events and said events
identified in no primary class dependence being secondary events, said set
D including related dependences which are isomorphic with a single graph G
having edges connecting vertexes, the vertexes of G corresponding to
events named in the events list data structure and the edges of G
corresponding to the dependences in the dependence list data structure;
(c) searching the dependence list and locating a first primary dependence
to serve as a root dependence for a tree;
(d) forming a primary event nucleus by selecting and attaching additional
primary dependences to said tree;
(e) adding secondary dependences in layers around the primary event nucleus
of said tree;
(f) assigning a time attribute to events in said tree, said time attributes
being consistent with the timing relationships specified in the set D of
dependence information;
(g) repeating steps (d), (e) and (f) to develop a time consistent graph T
having all the vertexes of graph G and with edges corresponding to
dependences in a set I of included dependences, I being a subset of G, a
dependence being in I if its interval corresponds to the difference in
time attributes of its two vertexes, the set I of included dependences and
the time attributes being subject to the conditions that:
(1) the number of primary class dependences from the set D included in I be
maximized;
(2) all primary vertexes be connected by a set C of core linkage
dependences, set C being a subset of I, the number of secondary
dependences in the core linkage set C being minimized;
(3) each secondary vertex S.sub.i be connected to a primary vertex by a set
P.sub.i of peripheral-linkage secondary dependences, set P.sub.i being a
subset of I, the number of secondary dependences in each
peripheral-linkage set P.sub.i being minimized;
(4) subject to the above conditions in (1), (2) and (3), the number of
secondary class dependences in I be maximized;
(h) providing design information from the time consistent graph T on the
display means; and
(i) applying the design information to aid in the design of said operation.
2. A method as claimed in claim 1, wherein said providing step includes
reporting those dependences in set D which are not in set I.
3. A method as claimed in claim 2, wherein said generating step includes
entering data characterizing dependence intervals as maximum or minimum,
and wherein said providing step includes reporting whether those
dependences in set D which are not in set I are violated.
4. A method as claimed in claim 1, wherein said generating step includes
entering signal sequence data about said operation, and wherein said
providing step includes reporting a timing pattern based on the graph T.
5. A method as claimed in claim 1, wherein said generating step includes
entering signal sequence data about said operation, and wherein said
providing step includes reporting events sequenced differently in graph T
than in the entered signal sequence data.
6. A method as claimed in claim 1, wherein said generating step includes
entering data defining a query as to time interval between two events and
wherein said providing step includes reporting such time interval as
indicated by the graph T.
7. A method as claimed in claim 1, wherein said generating step includes
entering data defining a timing pattern, and wherein said providing step
includes reporting discrepancies between said timing pattern and a timing
pattern implied by the graph T. |
|
|
|
|
Claims  |
|
|
Description  |
|
|
BRIEF SUMMARY OF THE INVENTION
This invention relates to the design of complex operations such as those
encountered in developing computers, and more particularly to assisting in
the resolution of timing problems in such designs.
The design of a complex operation such as a read operation of a computer
involves a number of interrelated timing specifications--200
specifications might be considered typical. Some of these specifications
arise from hardware limitations such as requiring that a stable input
signal to a device be established for a certain minimum time interval
before a stable output signal is achieved; others arise from system
requirements such as design cycle or operation time. Especially as such
specifications relating to an operation become more numerous, it can be
very difficult for a designer by inspection or analysis to tell whether a
given aggregate of specifications is internally consistent, and if not
where the trouble is. Frequently timing problems have been worked out only
by simulation of the operation or by building and exercising a prototype,
both rather expensive procedures.
The present invention describes method and apparatus for analysis of timing
requirements by identifying an optimized reduced set of requirements which
is self consistent and which is minimally reduced from the original.
BRIEF DESCRIPTION OF THE DRAWING
FIG. 1 shows an archetypal sequence pattern such as may be used to define
dependences used in the invention.
FIG. 2 shows a computer such as may be used to practice the invention.
FIGS. 3-8 show the flow diagram of a program according to the invention.
DETAILED DESCRIPTION
It is a frequent practice in analyzing the timing of computer operations to
define a sequence pattern giving a sequence of states for each of several
electrical points of the hardware system. The sequence pattern of an
operation provides a suitable framework for a systematic description of
its timing requirements. The particular set of states recognized in the
analysis may include, in addition to the high voltage and low voltage
states used for data signals, states indicating the electrical point is
indeterminate or in some transition, but the particular set of states is
not relevant to the present invention. The sequence for a particular
electrical point may be denominated the signal of the electrical point,
and a signal will thus be a sequence of states with each boundary between
succeeding states denominated an event. The aggregate of the signals may
be denominated a sequence pattern. When a sequence pattern is presented
against a time base common to all signals it is denominated a timing
pattern. Each event of a sequence pattern can be identified by giving the
name of its signal and its ordinality: Signal 3, 4th event. An archetypal
sequence pattern is shown in FIG. 1.
According to the invention, the timing requirements of an operation are
expressed with reference to a sequence pattern as a set of dependences.
Each dependence has a name, identifies a first event and a second event,
specifies a time interval between first and second events (which may have
a negative as well as a positive value), specifies a type for the
dependence, and specifies a class for the dependence. The dependence type
may be either "max" or "min" and characterizes whether the interval
specified between the identified events is a maximum or a minimum
requirement. The dependence class may be either primary or secondary and
characterizes two levels of importance for the specification as determined
by the analyst. An event which is identified in a dependence of primary
class will be designated a primary event; an event not so identified will
be designated a secondary event. It may be particularly noted that each
dependence involves only one time value. If it is desired to incorporate a
timing requirement of the form that some value lies between a lower and an
upper bound, it is necessary to express this requirement as two distinct
dependences--a max type and a min type.
The invention is conveniently practised using a computer as shown in FIG.
2. Computer 10 includes processor 11, memory 12, entering means, such as
keyboard 13, for entering data into the computer, and outputting means,
such as display 14, for outputting data from the computer. Processor 11,
memory 12, keyboard 13, and display 14 are constructed and interconnected
as well known in the art. Disk 15 may provide alternative means for
entering and outputting data. A program 16 stored in memory 12 provides
with processor 11 calculating means for calculating certain data as will
further described hereafter.
In practicing the invention, one first expresses the timing requirements of
an operation as a set of dependences and enters them into a dependence
file in the memory 12 of computer 10. The dependences may be entered
directly through keyboard 13, but it is usually more convenient to
formulate the dependences and represent them in a dependence file on a
disk and then enter the dependence file into the computer memory from the
disk. Output reports may also be specified at the outset and represented
on the disk. An advantageous format for expressing and entering the
dependences is
tSPEC,min,+13,signal 2-5,signal 22-14, secondary where tSPEC is the name of
the dependence; signal 12-5 identifies the first dependence event as the
5th event of the 12th signal; signal 22-14 identifies the second
dependence event as the 14th event of the 22nd signal; +13 indicates a
time interval of 13 units of time between these events; min indicates that
the time interval specified is a minimum (the alternative would be max for
maximum); and secondary indicates that the dependence is of secondary
importance (the alternative would be primary).
After the dependences have been entered a series of calculations are made
by the computer under control of the stored program. Before considering in
detail the operation of this program it will be useful to consider the
objective and results of the calculations.
The computations made according to the invention can be conveniently
explained by reference to the terminology of mathematical graphs. A graph
in this sense is a set of vertexes connected by a set of edges. It is
readily seen that a set of dependences as described above is isomorphic
with such a graph: the events identified in the dependences corresponding
to vertexes of the graph, and the association of events specified by a
dependence corresponding to edges of the graph. An arbitrary set of
dependences may correspond to a plurality of disconnected graphs. This
means, however, that there is no relationship specified by a dependence
between the events of one graph to those of another. Initially we consider
a subset D of dependences which are related and which are isomorphic to a
single connected graph G.
A further aspect of the isomorphism of the set of dependences and the graph
is that to every internal inconsistency of the set of dependences there
will be a reentrant path (or loop) in the graph. This can be readily seen
by considering that an inconsistency means that there are alternative
linkages (or paths in graph terminology) through the dependences between
two events, and these two linkages imply disparate time relationships
between the two events. Two alternative paths may however imply the same
time relationship so that such loops in the graph (denominated zero loops)
do not imply an inconsistency in the dependences.
The result of the operation of the program is to define a new graph T which
has vertexes which are the same as those of the graph G and which has
edges which correspond to a subset I of the dependences in D, and which
has a time attribute associated with each of its vertexes. The dependences
included in I (the included dependences) are chosen to meet the
conditions:
(1) the number of primary class dependences from the set D included in I be
maximized,
(2) all primary vertexes be connected by a set C of core linkage
dependences, set C being a subset of I, the number of secondary
dependences in the core linkage set C being minimized,
(3) each secondary vertex S.sub.i be connected to a primary vertex by a set
P.sub.i of peripheral-linkage secondary dependences, set P.sub.i being a
subset of I, the number of secondary dependences in each
peripheral-linkage set P.sub.i being minimized, and
(4) subject to the above enumerated conditions, the number of secondary
class dependences in I be maximized.
The result of the computation process is to define a set of dependences
which is a subset of the original set and is free of inconsistencies. The
subset is also optimized in the sense that the dependences of the original
set that are omitted are those least directly linked with the core of
primary dependences.
The steps of the computational operation are diagrammed in FIGS. 3-8. As
shown particularly in FIG. 3, the initial step is the inputting of the set
of dependences. The data structure for this list includes fields for:
Name; Type; Time interval; First event; Second event; Class; Used-flag;
Include-flag. The first six fields have been discussed earlier; the two
flag fields are used to keep track of the progress of the operations.
After the inputting of the dependences, the program generates an event list
from the dependence list. The data structure for the event list includes
fields for: Signal name; Event number; Time attribute; Mark. Of these, the
signal name and event number are directly derived from the dependence
list. The time attribute is calculated in the course of the program
operation. The mark parameter is used to indicate the status of the
calculation of the event. It may have values as follows: 0=uncalculated;
1=to be calculated; 2=adjusted; 3=calculated with primary dependence; 4
and higher=path distance to primary event. After generating the dependence
lists, the program goes to the "do calculations" diagrammed in FIGS. 4-8.
After an initial pass through the "link trees" module, the program finds a
primary dependence (FIG. 4, upper right) which serves as a root dependence
of a tree. The list of dependences is repeatedly searched and additional
dependences are then found and attached to expand the tree. As new events
are added, their time attributes are calculated so as to be consistent
with the interval specified in the dependence.
Dependences and events are added in layers around the initial root
dependence. (The layers are tracked with the "mark" flag.) First (with
successive passes around "build trees") the program connects additional
primary dependences to form a primary event nucleus. Then (with successive
passes around "build trees") secondary dependences are added in layers
around the primary event nucleus. When this process has been exhausted,
the program moves to "link trees" and finds all primary dependences
attaching to the layer of the then constructed tree which is innermost and
which has a vertex associated with an unattached primary dependence. These
newly attached primaries serve as secondary roots. The program reverts to
"build trees" and builds on the secondary roots in the same fashion as it
did on the original root: first adding primaries to form nuclei and then
secondaries in layers. When this processes is exhausted the program
reenters and repeats "link trees". And so on until all dependences have
been connected.
Certain features of the calculation deserve notice. When a dependence is
processed which attaches a previously unattached event (or vertex, in
graph terminology), the new vertex is assigned a time consistent with the
dependence. Such a dependence will therefore meet the definition of an
included dependence.
The organization of the search for secondary roots by examining layers
progressively outward on the then existing tree assures that the primary
vertexes will be connected through a minimum set C of core linkage
dependences.
When a secondary dependence is processed which bridges two already
connected vertexes this indicates that a loop is being completed. Neither
vertex is reassigned a time, and unless the loop completed is a zero loop,
the newly processed dependence will not have an interval consistent with
the time values assigned to its vertexes. Such a dependence does not then
qualify as an included dependence in set I. The order of processing, in
which secondary dependences are added in layers around a nucleus of
primary dependences ensures that the non-included secondary dependences of
a loop involving a single nucleus will be as far as possible from the
primary dependences. Loops involving a plurality of nuclei will initially
produce a non-included secondary dependence abutting the point where a
growing nucleus impinges on an already attached vertex. In subsequent
passes through "select events", however, the times assigned to vertexes is
revised to make the non-included dependence the one most distant from a
primary dependence. Together these arrangements of the order of processing
assure that every secondary vertex is connected to a primary vertex by a
minimum path of peripheral-linkage secondary dependences.
After the completion of the computations described above, a time consistent
graph T will have been constructed related to the original dependence set
and with the properties as discussed above.
In the preceding discussion it has been supposed that all the dependences
were related, that is to say connected in a single graph. If, however,
there are additional sets in the entered dependences unconnected to the
graph first processed by the program, these will be started (using the
program portion at the right of FIG. 4) after completing the original tree
and processed in the same manner to produce trees with the same
properties.
The next step according to the invention is to output information that is
useful in the design of the computer operation which has motivated the
calculation. The designer can address individual and specific inquiries
through the keyboard or use program modules to generate systematic
reports. The techniques for implementing such outputting of information
are well known and need no explication here. It will be worth while,
however, to point to some outputs which are particularly useful.
Probably the output information of preeminent interest to a designer is a
list of the non-included dependences, these being those from the
originally entered set D which are not included in the set I. In
particular, if this list is empty it means that the originally entered set
of dependences are consistent. If the list is not empty it identifies the
inconsistencies and promising dependences for revision. Whether
non-included dependences are violated or not may also be usefully
reported. A violated dependence is one of type max for which the interval
implied from the graph T is greater than that specified or one of type min
for which the implied interval is less than that specified.
When signal sequence data has been inputted, a report of a timing pattern
may be obtained in which events of various signals are displayed against a
common time base.
When signal sequence data has been inputted, a report of out of sequence
events may be obtained.
A report may be obtained of the interval between specified events which are
not included dependences.
A timing pattern may be inputted and a report output of discrepancies with
the timing pattern implied by the graph T.
* * * * *
|
|
|
|
|
Description  |
|